Reconstruction and restoration of the cultural heritage site "Tsentralny Stadium" with a capacity of 35,000 seats for the 2018 world Cup in Russia. The architectural concept of the stadium is based on a combination of preserved and restored architecture of the historical walls of 1954 and the embedded core of the new stadium. The facades of the new stadium have an emphatically neutral architecture, which is the background for the perception of the historical facades of the stadium. On the West and East sides, between the historical wall and the new core, there is a kind of atrium space (an open gallery) that serves as an entrance area for the audience, from which they begin to move to their seats via cascading stairs. The facade of the new volume is lined with perforated metal panels, the horizontal divisions of which, as well as the different diameter of the perforation, allows you to visually ease the volume and make it lower than its real size. The Yekaterinburg Arena, defined under the word "HISTORY - CONTINUITY-INNOVATION", is a new indicator of the modern sports arena.
2018 러시아 월드컵에 맞춰 세워진 예카테린부르크 축구경기장은 문화유적지 ‘첸트랄니 스타디움’이 재건축된 것이다. 1954년의 역사적 가치를 지닌 성벽을 보존하고, 복원하면서 현 시대에 맞는 운동 경기장과 결합하는 것이 중요한 프로젝트였다. 예카테린부르크 경기장 정면 파사드에는 “시대 중립적인” 구조물이 드러나면서, 이 공간이 가진 역사를 지켜보게 만든다. 서쪽과 동쪽에는 역사 벽과 새로운 중심부 사이에 관객들의 출입구 역할을 하는 일종의 아트리움 공간(열린 갤러리)이 있고, 여기서부터 연속된 계단을 통해 자리로 이동하기 시작한다. 새로운 공간의 전면에는 타공판으로 만들어진 패널이 나열되며, 이러한 공간의 분할은 스타디움이라는 대형 경기장을 실제 크기보다 작게 보이게 만들어 친숙한 공간으로 느끼게끔 한다. 역사, 지속성, 혁신이라는 단어 아래 정의되는 예카테린부르크 아레나는 현대적 스포츠 경기장의 새로운 지표가 된다.
Architect PI-ARENA
Location Yekaterinburg, Sverdlovsk, Russia
Program Football stadium
Site area 11ha
Building area 31,440.00㎡
Gross floor area 166,300.00㎡
Height 45m
Capacity About 45,000
Design period 2014. 3 - 2017. 6
Construction period 2014. 11 - 2017. 12
Completion 2017
Principal architect Dmitry Bush
Project architect Oleg Gak Architect Alexey Orlov, Anton Zaklyuchaev, Daria Petkova, Alexandra Sibiryakova, Anastasia Podrez, Elsa Shikhragimova, Agatha Kudamanova, Maria Morozova, Oleg Tsai, Tatiana Elfimova, Andrey Tsyplakov, Sergey Korobkov
Master plan Kristina Kharitonova
Structural engineer (CS Section) Alexey Shakhvorostov_Inforsproekt Company/(MC section) Anton Kuleshov_Maximum Company
Mecanical engineer Erlan Bekmukhamedov, Natalia Shalygina, Alexey Ivanov
Electrical engineer Mikhail Kislov
Visualization Pavel Kuritsyn, Vadim Kuchuk, Maksim Arkhipov
Construction JSC "Sinara-Development"
Client FGUP "Sport-Engineering", "Department of Sverdlovsk region capital construction"
Photographer JSC Sinara development
해당 프로젝트는 건축문화 2021년 9월호(Vol. 484)에 게재되었습니다.
The project was published in the September, 2021 issue of the magazine(Vol. 484).
'Architecture Project > Other' 카테고리의 다른 글
MANTINUM INTERVENTION (0) | 2022.02.11 |
---|---|
MAUSOLEUM OF MARTYRDOM OF POLISH VILLAGES (0) | 2022.02.10 |
FOOTBALL STADIUM SAMARA-ARENA (0) | 2021.12.13 |
FOOTBALL STADIUM VOLGOGRAD-ARENA (0) | 2021.12.10 |
OLYMPIC STADIUM FISHT (0) | 2021.12.09 |
마실와이드 | 등록번호 : 서울, 아03630 | 등록일자 : 2015년 03월 11일 | 마실와이드 | 발행ㆍ편집인 : 김명규 | 청소년보호책임자 : 최지희 | 발행소 : 서울시 마포구 월드컵로8길 45-8 1층 | 발행일자 : 매일